Hainan Refining-chemical Reconstruction and Expansion Project
Located in the Yangpu Economic Development Zone, Danzhou, Hainan, the scale is 120000 m³/d. 12 sets of the systems are used in and each scale of the system is 437.5 t/h with the grid flocculation, inclined tube sedimentation and V-shaped filter. The project gives full play to the characteristics of Modular Water Purification System, such as smaller floor area, shorter construction period and higher degree of automation. The construction was officially started on May 7, 2021, and the modular water purification plant system, auxiliary pipelines, electrical instruments, flocculant dosing system and disinfectant dosing system were completed on November 15 of the same year.After 10 days, i.e. November 25, the water inflow commissioning is qualified.